Port Authority Bus Terminal Construction: What Changes on West 39th Street

On West 39th Street between Ninth and Tenth Avenues, the north lane now belongs to buses. Since Thursday, October 15, buses coming from the Lincoln Tunnel and Dyer Avenue have left the ramp system on a newly built slip ramp. They travel west along the street and rejoin the ramps near the northeast corner of 39th Street and Tenth Avenue. Ordinary through traffic is gone from the block. The walkway and bike lane have moved south to make room.

The point of the $11 billion Midtown Bus Terminal replacement is to get buses off neighborhood streets. The Port Authority says the new ramp structure "will keep buses within the terminal, reducing congestion and minimizing their presence on city streets." Getting there takes years of temporary arrangements in which buses become more visible on a few specific blocks. The first of those arrangements is now in place. For residents of Hell's Kitchen's southern edge, the next five years will be shaped by this interim street map more than by the finished terminal.

How the Block Between Ninth and Tenth Works Now

The Port Authority's October 13 travel advisory lays out the arrangement in detail. Here is how the block works for anyone who walks, bikes or drives it:

  1. Buses enter at Dyer Avenue and 40th Street. They exit onto West 39th through the new slip ramp and go back into the ramp system from the north lane near Tenth Avenue without stopping at the signal.
  2. Cars and trucks can use the block only if they are local or directly serving businesses on 39th Street between Ninth and Tenth. Near Tenth Avenue they use a south lane to go straight or turn right, as the signal directs.
  3. Pedestrians and cyclists still use 39th Street, on a walkway and bike lane that have been moved south.

The agency says it designed the setup with the city's Department of Transportation to limit congestion. It also expects local traffic effects on 39th and 40th Streets and on Ninth and Tenth Avenues. The amNewYork preview pointed out that the morning exclusive bus lane through the tunnel runs on a separate ramp and is not affected. On the day the change began, PIX11 reported that commuters described longer trips through the work zones between Ninth and Tenth. Some riders said slowdowns had been noticeable since summer, so the delays predate this particular change.

Why Buses Had to Move Onto the Street

The detour exists because the old ramps are coming down. They sit inside the footprint of the future storage and staging facility, which also serves as the temporary terminal, so they have to be cleared before that building can go up. Buses need a route around the demolition, and West 39th Street is that route.

The first ramp scheduled for removal is E-96. It carries buses into the terminal from Dyer Avenue as they leave the Lincoln Tunnel, and from 40th Street. A community construction update dated October 16 gives the plan for the contractor, Tutor Perini:

  • On or about October 24: work begins. The ramp comes out in three sections, with concrete removed first and steel second for each section. Shifts run during the day and overnight.
  • Daytime: limited hoe ramming to break apart the abutments between sections. The notice says this will be noisy.
  • Overnight: saw cutting on all three sections. Section 1 is cut only at night, while sections 2 and 3 are cut day and night. Crews also use "coring," which drills holes so cranes can lift sections out. The Port Authority describes both methods as quieter.
  • Mid-December: most of the concrete removal is expected to be done.
  • End of 2026: the steel beams are expected to be gone.

The worksite will be surrounded by sound-absorbing blankets. The agency says it is favoring daytime shifts to cut overnight noise and expects noise to drop once crews move from concrete to steel. The same notice warns of extra bus traffic on Ninth Avenue between 39th and 40th Streets. Parts of Dyer Avenue may close alongside regular Lincoln Tunnel closures, with further notices to follow.

On a Thursday late in October, the corner of Ninth and 39th has two layers of activity at once. Buses on the new detour pass by while the first ramp comes apart behind blankets a short distance away.

West 40th Street Gets a Stack of Ramps

One block north, the temporary setup goes up instead of sideways. The Port Authority asked to build temporary ramps along and above West 40th Street between Galvin Plaza and Dyer Avenue. They will carry buses in and out while the interim terminal, the permanent ramps and the new main terminal are built. Manhattan Community Board 4 approved the request on March 4 by a vote of 45 to 0.

The approval came with conditions, and those conditions show what the board considers most at stake. In its March 13 letter to the Department of Transportation, CB4 noted that the Port Authority had changed its design and stacked the two ramps. That leaves about 30 feet between the ramps and the mixed-use buildings on the street's north side. "We are happy with this," the board wrote. The board then made three requests:

That the expiration date of this temporary consent be specified as "no later than a certain date" rather than being left so open-ended that the PANYNJ may choose to keep using the ramps.

The other two requests asked for enough lighting and enclosures beneath the ramps to keep that space safe, and for the ramps' traffic signals to be aimed so they do not shine into apartments on the north side.

The first request deals with timing. The board asked that the date for taking the ramps down be stated explicitly, not left open-ended.

What the Interim Period Is Supposed to Produce

The deck-over above Dyer Avenue is further along than most of the work visible from the street. According to the Port Authority's project updates, two of the deck's four quadrants are almost fully decked, and steel for an interim ramp is going in. A summer construction report from New York YIMBY documented demolished ramps, reduced bus access lanes, and rebar and fencing on the deck-over between 38th and 39th Streets.

The deck-over is also where the neighborhood's eventual benefit is supposed to come from. While construction continues, it will handle temporary bus operations and passenger service. After the main terminal is finished, the Port Authority has committed to turning it into 3.5 acres of publicly accessible open space. The agency's dated schedule puts the end of phase one, covering the deck-over, the storage and staging facility and the new ramp structure, at the close of 2030. The new terminal on Eighth Avenue follows by 2035. No design or program for the open space has been released. The project materials list public art, retail facing the street and safer, more walkable streets among the intended benefits.

This explains the unusual order of events. The same land does three jobs over about a decade: it carries a deck, then holds buses temporarily, then becomes a park. Each stage needs a temporary street arrangement, and the one on West 39th Street is the first.

The Corner Where It All Meets

At Ninth Avenue and West 39th Street, the building that many neighbors know as Cassa is now Truss Hotel Times Square. W42ST reported that it changed hands after a mortgage dispute and is under new management. Signs in its windows advertise an incoming steakhouse. The building also holds apartments and commercial space. It faces the block where buses now run and is close to the stretch of Ninth Avenue where the E-96 notice expects extra bus traffic.

Ninth Avenue is also changing. In March, the Department of Transportation announced a permanent redesign of Ninth Avenue. The plan adds nine feet of pedestrian space, widens the protected bike lane from five feet to nine, and adds a rush-hour bus lane, with a late-summer or early-fall completion target. The avenue's new layout and the terminal's temporary routes are being set at the same time on the same blocks.

To follow the next step, the Port Authority posts lane-closure and construction notices on its project updates page, and residents can sign up for advisories by emailing [email protected]. The next milestone in the notice is mid-December, when most of E-96's concrete is expected to be removed.

If you own near West 39th or 40th Street and want to know how this construction timeline, from ramp removal through the 2030 phase-one date, might affect your plans for a sale or purchase, the Luxury Advisory Team would welcome the conversation. Schedule a private consultation.

Work With Us

Whether working with a local, national, or international client, the Luxury Advisory Team will guide and advise you from the beginning to the end of your real estate transaction, make every transaction a luxury experience.

Follow Me on Instagram